UPDATED: Plumsted Twp Sewer Construction Dates
Sewer Work - Projected Dates by Street (updated 8/27/20)
Posted on: June 15, 2020 - 5:07pm
Allen Terrace | complete, final paving |
Bell Street | complete, final paving |
Brindletown Road | complete, final paving |
Church Street | complete, final paving pending |
Crystal Avenue | complete, final paving |
Earley Drive | complete, final paving |
Evergreen Road | complete, final paving |
Front Street | complete, final paving |
Jacobstown Road | complete, final paving |
Lakeview Drive | complete, final paving* |
Lakewood Road | complete, final paving |
Locust Lane | complete, final paving |
Main Street (East of creek) | complete, final paving pending |
Main Street (West of creek) | complete, final paving pending |
Maple Avenue | complete, final paving |
Marketplace Driveway | complete, final paving |
North Main Street to Main Street | complete, final paving |
Terrace Avenue (off of Twin and off Lakeview) | complete, final paving |
Twin Drive | complete, final paving |
Night work: Main Street - 3 or 4 nights during Main Street West work.
*Lakeview Drive between Main Street and Oakford Drive paving pending.
All dates are approximate and subject to change due to inclement weather.
Plumsted Township never sends unsolicited email.
You received this message because you requested a subscription to receive email alerts from Plumsted Township.