UPDATED: Plumsted Twp Sewer Construction Dates

Sewer Work - Projected Dates by Street (updated 8/27/20)

Allen Terrace

complete, final paving
Bell Streetcomplete, final paving
Brindletown Roadcomplete, final paving
Church Streetcomplete, final paving pending
Crystal Avenuecomplete, final paving
Earley Drivecomplete, final paving
Evergreen Roadcomplete, final paving
Front Streetcomplete, final paving
Jacobstown Roadcomplete, final paving
Lakeview Drivecomplete, final paving*
Lakewood Roadcomplete, final paving
Locust Lanecomplete, final paving
Main Street (East of creek)complete, final paving pending
Main Street (West of creek)complete, final paving pending
Maple Avenuecomplete, final paving
Marketplace Drivewaycomplete, final paving
North Main Street to Main Streetcomplete, final paving
Terrace Avenue (off of Twin and off Lakeview)complete, final paving
Twin Drive complete, final paving

Night work:  Main Street - 3 or 4 nights during Main Street West work.

*Lakeview Drive between Main Street and Oakford Drive paving pending.

All dates are approximate and subject to change due to inclement weather. 